RE: [10GBASE-T] September interim meeting
Bruce,
 
I think I 
agree that data centers are enough to fulfill broad market potential for 
10GBASE-T. For some years to come, I think that (plus perhaps some 
switch-to-switch connection if the media and distance supports it) would be the 
main volume.
 
On power, I don't 
mean that someone needs to show that they can produce today a low power 
10GBASE-T transceiver. While the first 1000BASE-T transceivers used an 
uncomfortable amount of power, I don't think they used so much that I couldn't 
put them on a card.
 
I'm not expecting 
exact numbers. What I would like to see for PAR approval is some estimates from 
potential implementers to show that, given expected technology 
improvements over the next couple of years, it will be possible to produce 
transceivers (in about the time frame that we expect to be finishing the 
standard) that can be used on a card - though perhaps at levels higher than 
those we would all like to see long run. 
 
There are times when 
we goof and standardize something that is so far from what the market needs that 
it doesn't have enough volume to get produced and improved. There are other 
times where the initial parts aren't ideal but they are good enough to start 
building a market and invest in improving it. The first 1000BASE-T PHYs were at 
least good enough to be deployed. I would like a reasonable comfort level that 
the 10GBASE-T PHYs will be over that hump.
 
Regards,
Pat
  Pat
Thanks for providing detail on data 
  centers. I would argue that in terms of broad market potential, 10GBASE-T 
  would pass muster even if the only market application was data 
  centers.
On the power issue, the first 1000BASE-T implementations did 
  not appear until well after the standard was done, some 5 years after the High 
  Speed Study Group got its PAR, and consumed an obscene about of power. We 
  might have never achieved the  low power 1000BASE-T PHYs we have today if 
  we had tried to agree on exact numbers in 1996.
Bruce
At 11:00 
  AM 7/31/2003 -0600, pat_thaler@agilent.com wrote:
  Nariman,
 
CX4 is useful 
    especially when we have in rack connections to make or ones going to the 
    next rack. However, the distance is too short for many other data center 
    connects. Also, the cable for the long distance is relatively bulky which 
    may be a problem for some uses. We will be glad to get it, but it only 
    solves a corner of the problem space.
 
Something for the longer distances in data centers that is lower cost 
    than fiber would be useful. For that environment, it doesn't necessarily 
    have to rely on already installed wiring. Running on existing wiring is 
    nice, but not essential.
 
My view 
    of the important items for the data center 
    environment:
 
It must perform 
    solidly on the media we choose for it - data integrity factors such as BER 
    must be met.
It must be able to live on 
    "standard" server bus adapter formats with a TOE: e.g. PCI Express and 
    Infiniband
    which means 
    power is a concern
It must be transparent 
    to existing MACs - that is, the MAC must see the same behavior it sees with 
    10 Gig fiber.
100 m would be desireable 
    (partly to enable future horizontal usage) but the data center could live 
    with shaving something off that. (100 m is nice from a standards development 
    standpoint as it saves us from arguing about what lower number is 
    enough.)
The media it runs over should not 
    be so stiff or bulky that it is a problem to accomodate with normal rack and 
    data center cable management.
Of couse it 
    must also meet EMI requirements
 
Regards,
Pat 
    
      - -----Original Message----- 
      - From: Nariman Yousefi [mailto:yousefi@broadcom.com] 
      - Sent: Wednesday, July 30, 2003 8:10 PM 
      - To: pat_thaler@agilent.com; btolley@cisco.com; 
      bradley.booth@intel.com; stds-802-3-10gbt@ieee.org 
      - Subject: RE: [10GBASE-T] September interim meeting
 
 
- Pat,
 
 
- I agree that the issues you raised must be addressed by November. One 
      of the biggest challenges for this group is to establish reality on 
      technical feasibility on Cat7, Cat6 and Cat5e channels.  Different 
      vendors have different conclusion on Technical feasibility. That is due to 
      assumptions on alien cross talk mitigation techniques, impact on 
      implementation impairments on SNR, channel model, coding gain, and 
      analysis on chip complexity in a given process. Assumptions must be stated 
      clearly by vendors that present technical feasibility. In this case, 
      technical feasibility drives the broad market potential.  Technical 
      feasibility must be addressed at least based on the following 
      criteria:
 
 
- 1. Achievable distance on Class D channel with and without 
      installation mitigation techniques. 
      - 2. Achievable distance on Class E channel with and without 
      installation mitigation techniques. 
      - 3. Transceiver complexity in terms of estimated power dissipation and 
      realistic targets for building blocks like ADC, PLL and etc 2-3 years from 
      now.
 
 
- We reached a conclusion that cat7 cable or class F channel has high 
      enough capacity for 10Gbps operation.  But, can a transceiver be 
      built with reasonable power dissipation and cost say in 90nm process or 
      finer geometries to achieve broad market potential? 
 
 
- We need to keep in mind that customers have fiber and CX4 as 
      alternatives.
 
 
- Nariman
 
 
 
 
 
 
 
 
- At 01:08 PM 7/30/2003 -0600, pat_thaler@agilent.com wrote:
      
        - Bruce,
-  
        - Generally, when the group can agree on clear objectives, then they 
        can finish the rest of the work. Fuzzy objectives often indicate a lack 
        of real concensus.
-  
        - In November, I will also be expecting arguments that support the 5 
        criteria based on the objectives - 
- especially:
- Broad market potential - evidence that there will be a broad market 
        the minimum requirements of the objectives are met.
-  
        - Technical feasibility - is it feasible to meet those minimum 
        requirements
-  
        - Economic feasibility - when you have met the minimum requirements 
        will cost be suitable to make it a viable product in the markets? 
-  
        - In the discussions at the plenary, a power consumption issue was 
        raised by some of the speakers. 
- If the broad market potential is based in part on use in devices 
        such as end nodes (including servers in data centers), then an objective 
        for power consumption such that this can reside in server card formats 
        would be important. Can it fit within the power constraints of a PCI 
        Express board and an Infiniband board (remembering that one has to allow 
        some power for the MAC and probably TOE/RDMAP engine)?
-  
        - Looking at the objectifves in agenda_1_07_03, I don't see any that 
        address power consumption or the abilitiy to live on server card 
        formats. In a quick search, I also didn't find any material on power 
        consumption in the presentations that have been made to the study group. 
        I hope that in September the group will address the issue of 
        power.
-  
        - Regards,
- Pat
- -----Original Message----- 
        - From: Bruce Tolley [mailto:btolley@cisco.com] 
        - Sent: Monday, July 28, 2003 1:22 PM 
        - To: Booth, Bradley; stds-802-3-10gbt@ieee.org 
        - Subject: Re: [10GBASE-T] September interim meeting
 
 
- Brad:
 
 
- Thanks for the follow up.
 
 
- I am confident that if we can agree on crisp, clear objectives for 
        10 Gbps reach and media supported in September that we can get our PAR 
        approved and move into Task Force mode, which is where the real work 
        begins.
 
 
- Bruce
 
 
- At 06:35 PM 7/24/2003 -0700, Booth, Bradley wrote:
 
 
          - Study Group Members,
 
 
- Just to let others that were not at the meeting know the outcome 
          of the 802.3 Working Group meeting, the Study Group will have to 
          complete its PAR, 5 Criteria and Objectives in November.  This 
          gives the Study Group the task of completing the PAR, 5 Criteria and 
          Objectives in 4 months.  This will make our September Interim 
          meeting extremely important.  We will need to complete the effort 
          as much as possible to pre-submit to the 802.3 Working Group prior to 
          the November Plenary.  November will permit us the ability to 
          modify the PAR, 5 Criteria and Objectives prior to asking 802.3 to put 
          the PAR on the NesCom agenda.  The September Interim meeting will 
          focus on the completion of our PAR, 5 Criteria and Objectives. 
          - Thanks,
- Brad
 
 
- Chair, 10GBASE-T Study Group
 
 
 
 
- Bruce Tolley 
        - Senior Manager, Emerging Technologies 
        - Gigabit Systems Business Unit 
        - Cisco Systems 
        - 170 West Tasman Drive 
        - MS SJ B2 
        - San Jose, CA 95134-1706 
        - internet: btolley@cisco.com 
        - ip phone: 408-526-4534 
        - "Don't put your hiking boots in the oven unless you plan on eating 
        them."
 
 
- Colin Fletcher, The Complete Walker 
  
Nariman Yousefi
Vice 
  President Networking Engineering
PH  (949) 585 5450
FAX (949) 
  453 1848
e-mail : Yousefi@Broadcom.com 
  
  Bruce Tolley
  Senior Manager, Emerging Technologies
  Gigabit Systems Business Unit
  Cisco Systems
  170 West Tasman Drive 
  MS SJ B2
  San Jose, CA 95134-1706
  internet: btolley@cisco.com
  ip phone: 408-526-4534
  "Don't put your hiking boots in the oven unless you plan on eating 
  them."
  Colin Fletcher, The Complete Walker